An Inside Look: August At OHB
Welcome Back to An Inside Look!
Our portfolio shows you our work, our social media shows our culture, An Inside Look shows you everything in between!

As August is the 8th month of the year, here's 8 updates from our active sites.
1. 701 Hill — Demolition is behind us, and the crew has moved straight into foundation work. Footings are poured, and the foundation walls are going up now.
2. 534 S Brainard — The foundation is backfilled and ready. Sewer and water lines go in this week, with framing set to start right behind it next week.
3. 332 Fuller — Excavation and foundation are both complete, and framing is well underway — the first floor is finished, and the crew is heading into the second.
4. 613 Franklin — The driveway is poured and landscaping is taking shape outside. Inside, cabinets, countertops, and trim are all installed, and paint work is underway.
5. 610 Oak — Siding is fully up and landscaping has started. Trim is in too, though we're waiting on cabinets before the next round of interior work can move forward.
6. 614 Oak — A few doors down, hardwood flooring is in and tile work is underway. Masonry is finished outside, and siding will start soon — though like 610 Oak, this one's also waiting on cabinets, so we'll be curious to see which house gets there first.
7. 506 Carleton — Drywall is finished and the house is primed. Hardwood flooring is going in now, and landscaping has started outside.
8. 2S360 Madison — Trim work looks to be wrapping up, and the crew is installing tile across the walls this week.
Here's to another month of proving we can be 8 places at once!
It's the people who make this place what it is, on the sites and off.